File 122-7-193-09-1
Contractor | Roy Const & Supply |
Awarded | Feb 7/62 |
Contract comp date | August 15/62 |
Value of contract | $170,000.00 |
Value of work completed July 31, 1962 | $130,000.00 |
Current estimated completion date | August 31, 1962 |
Access Road | Complete |
Tower Fnds | Complete |
Tower Erection | Not started |
Acc Bldg | Fnds complete Floor slab poured Bldg erected Elect & Mech installations underway |
Radar Bldg | Same status as Acc Bldg |
Passageway | Fnds poured Framing complete Roofing and and siding not started |
Building Site | Rough grading complete Fencing not started Brush control complete |
Fuel Tanks | 2000 gal tank complete except for painting and piping 50,000 gal tank dyke complete Tank erection underway, to be completed August 10 |
Diesel Generator | Not shipped - expected to arrive on site week of August 12 |
Recommendation re termination of contract:
All work should be completed except: